905 Don Mills Construction Update

  • The site will be running daily, weather permitting following all local by-laws.
  • Delivery trucks will be visiting the site regularly delivering components for the building’s Interior Finishes Drywall, electrical, HVAC, and plumbing systems.
  • The material hoist was demobilized late December 2022
  • The mechanical penthouse roof screen installation shall continue this month.
  • Mechanical & electrical rough ins are complete throughout the building. They are working on finishes and commissioning of systems.
  • Drywall taping, mudding, and sanding will continue in the hoist suites, common areas and corridors are complete up to 9 T-bar ceilings are being installed ground floor through 6
  • Suite doors & trim are now complete up level 10. Kitchen & bathroom cabinets complete up to 10. Drywall checkout and cleaning on 2nd floor suites with appliance installation follow.
  • Suite door lock installation on 2nd floor moving to 3rd
  • Suite flooring complete up to 10
  • Elevator #1 is operational elevators 2, 3, & 4 scheduled to be online late March 2023
  • Installation of city curb and sidewalk on Don Mills is complete. City sidewalk remediation is complete on Green Belt Drive, with public access. Remaining soft scape will commence in the spring.
  • Overall building is complete, working on interiors. Remaining exterior finishes and landscaping to be completed in the spring.

Traffic / Noise

  • Crews will be on site five days a week (Monday – Friday); though not currently scheduled, some Saturday work might occur.
  • All work will be completed from Monday to Saturday as per our permit and in accordance with the City of Toronto bylaws.
  • When needed, we will have trained traffic controllers and Paid Duty Officers as required on our site to guide our trucks and local traffic safely and efficiently.
  • There one site entrance on Green Belt Drive, which receive most the vehicular traffic, now that adjacent hydro lands are no longer occupied.
  • Intermittent sidewalk and lane closures may occur.

Site Safety Measures

  • Overhead protection has been removed now that the building structure is complete. Fast fence is now in place for public right of way to protect pedestrian traffic.
  • Signage, barriers, fencing, pylons, and traffic control personnel will all be utilized on the site to ensure the safety of pedestrians and motorists.
  • Please obey any signs or traffic control personnel when near this site. They are all there for your safety.

Thank you for your continued patience and cooperation.